Active Projects

Recovery.gov
Filter Projects By:
Project Type
County
Value of Projects Given Notice to ProceedNumber of Projects Given Notice to Proceed
$1,025,383,276299
I-85 FM PLEASANT HILL RD TO OLD PEACHTREE RD-ATMS COMM/SURVE
Type:  Safety
Congressional District:  7
County:  Gwinnett
State Project Number:  110720-
Contractor:  R. J. HAYNIE & ASSOCIATES, INC.
Economically Distressed Area:  No
Scheduled Start Date:  09/18/2009
Scheduled Completion Date:  10/31/2010
Stimulus Funds:  $2,164,670
ATMS: COLUMBUS/MUSCOGEE COUNTY/GDOT REGIONAL TCC
Type:  Safety
Congressional District:  2
County:  Muscogee
State Project Number:  323005-
Contractor:  METROPOWER, INC.
Economically Distressed Area:  No
Scheduled Start Date:  02/11/2010
Scheduled Completion Date:  06/30/2011
Stimulus Funds:  $1,723,641
ATMS/SIGNAL/CCTV/FIBER IN COLUMBUS
Type:  Safety
Congressional District:  2
County:  Muscogee
State Project Number:  323000-
Contractor:  METROPOWER, INC.
Economically Distressed Area:  No
Scheduled Start Date:  02/11/2010
Scheduled Completion Date:  06/30/2011
Stimulus Funds:  $1,723,641
I-85 @ SR 324/GRAVEL SPRINGS RD 4.5 MI SE OF BUFORD
Type:  Congestion/Capacity
Congressional District:  7
County:  Gwinnett
State Project Number:  142285-
Contractor:  STRICKLAND & SONS PIPELINE, INC.
Economically Distressed Area:  No
Scheduled Start Date:  09/04/2009
Scheduled Completion Date:  05/31/2012
Stimulus Funds:  $11,755,255
I-675 ATMS/COMM/SURVEIL FM I-75/HENRY TO I-285/DEKALB
Type:  Safety
Congressional District:  13, 5
County:  Clayton, Dekalb, Henry
State Project Number:  714095-
Contractor:  WORLD FIBER TECHNOLOGIES, INC.
Economically Distressed Area:  Yes
Scheduled Start Date:  08/18/2009
Scheduled Completion Date:  04/30/2011
Stimulus Funds:  $1,894,363
Change Page:  < > | Displaying Page 1, items 1  to  5